FINANCIAL DATA FOR PROJECT PCT13277 as at 05/05/2014 28/05/2014
Council Approved Budget (all years): $14,800,000 $14,800,000
Expenditure to date (all years including committals) $20,248,336 $20,314,230
Preconstruction: External Design Phase Contracts $1,442,431 $1,442,431
Construction: External Contracts/Orders to Cairns
Works
$17,536,025 $17,536,025
(+) Variation additions as at 28/05/2014
(-) Variation deductions as 28/05/2014
Actual Expenditure to Date $10,948,713 $14,210,094
ESTIMATED TOTAL PROJECT COST AT
COMPLETION:
$19,953,586 $19,953,586
NOTE: Budget will need to be allocated in the 2014/15 capital works budget to
complete the works. Total projects costs excludes the contingency allowance of
$500,000 which may not be spent. Variations (both plus and minus) to Cairns Works
have not exceeded their existing orders and are reported to the Steering Committee.
Expenditure to date includes the end of north accrual figures

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s